Daewoo Nexia

since 1994 of release

Repair and car operation



Deu Neksiya
+ Maintenance instruction
+ Maintenance
+ Engine
+ 3. Engine (two top camshafts)
+ cooling System
+ Toplevnaya and exhaust systems
+ Electric chain
+ 7. Ignition system
+ 8. Electronic control unit and sensors
+ Transmission
+ 10. Five-speed transmission and main RPO MM5 broadcast
- 11. Automatic Transmission
   11.2. The terms, the accepted reductions and abbreviations
   11.3. General description of transmission
   11.4. Main knots of a transmission
   11.5. Methods of localization of leakages of working liquid
   11.6. Check of level of working liquid in transmission the 4Т40th
   11.7. Diagnostics of malfunctions of knots of transmission
+ Steering
+ Running gear
+ 14. Forward suspension bracket
+ 15. Drive of forward wheels
+ 16. Back suspension bracket
+ Brake system
+ Body
+ Heating, ventilation
+ Electric equipment


8128da4b



11.6. Check of level of working liquid in transmission the 4Т40th

GENERAL INFORMATION

Control of level of working liquid of transmission

 


Level of working liquid is checked on heated-up transmission (the temperature of liquid should be not less than 40 ° C). Preliminary warming up of transmission is made as follows.

PERFORMANCE ORDER
1. To get the car on the lift or a viewing hole. The car should settle down horizontally that results of check of level of liquid were correct.
2. To place suitable capacity under an opening stopper for control of level of liquid.
3. To start the Engine and let's to it work idling about 5 minutes. If there is a possibility, it is possible to warm up also transmission by car run on distance of several kilometers.
4. At the pressed brake pedal consistently to pass the selector of ranges of a transmission all provisions, maintaining in each situation a pause in some seconds. Then to return the selector to situation P (Parking).
5. To turn out a stopper of a control opening. Normal level of working liquid can be as above, and edges of a control opening are lower. In the first case liquid will follow from a control opening.
Prevention

The effluence of hot working liquid from a control opening can lead to burns.


At a liquid effluence from a control opening it is possible that Transmission was overflowed. After the leak of liquid from an opening stopped, level of working liquid in a case will correspond to norm. To establish into place a stopper and to tighten it the moment of 12 Nanometers.
If working liquid does not follow from an open control opening, it is possible that liquid level in transmission is lower than norm. In this case it is necessary to pour in through a jellied opening in a case working liquid in the small portions (on 0,5 l) prior to the beginning of its effluence from a control opening, but only no more than 1,5 l. If thus liquid started to follow from a control opening, its level was in norm.
Let's to superfluous liquid merge completely from a control opening and to establish into place a stopper. To tighten a stopper of a control opening the moment of 12 Nanometers.
If after addition of one and a half liters level of working liquid did not rise to the bottom edge of a control opening (liquid does not follow from a control opening) it means that level of working liquid about transmission was lower than norm. Leakages of working liquid are possible also. It is necessary to examine transmission on existence of traces of leaks and to eliminate all found malfunctions before leading up level of working liquid to norm.
6. After completion of check of level of working liquid to wipe rags traces of smudges on a surface of a case of transmission. To check correctness of installation of a cover of a jellied opening and a ventilating tube.

Having added working liquid to normal level after transmission repair

PERFORMANCE ORDER
1. Depending on type of repair it is necessary to pour in in a transmission charter working liquid in the following quantity.
The repair connected with demontazhy of the pallet of a case of transmission (without removal of transmission from the car) – 7 l.
Hydrotransformer replacement – 2,5 l.
The repair connected with complete dismantling of transmission – 10 l.
2. To execute operations with the first on the fourth on check of level of working liquid.
3. Through a jellied opening to pour in in a case working liquid in the big portions (on 0,5 l) prior to the beginning of its effluence from a control opening.
4. Let's to superfluous liquid merge completely from a control opening and to establish into place a stopper. To tighten a stopper of a control opening the moment of 12 Nanometers.
5. After finishing of level of working liquid to norm to wipe rags traces of smudges on a surface of a case of transmission. To check correctness of installation of a cover of a jellied opening and a ventilating tube.